Audit Division
Audit
Summary
Public
Works Board
Lied
Library Project
Report LA02-07
Results in Brief
|
The
State Pubic Works Board did not always comply with existing project management
standards. Furthermore, additional
standards are needed to help ensure projects are completed within budget and on
schedule. Additional costs and delays
on the Lied Library project may have been avoided if the SPWB had adhered to
appropriate project management standards.
The Board lacks formal policies and procedures to ensure open competition and the proper evaluation of contractors’ qualifications. As a result, the SPWB did not use a competitive process to select the project’s architect or determine the qualifications of contractors that submitted bids. Furthermore, construction monitoring guidelines are not adequate. Key elements of an effective monitoring process include resolving problems that may result in reduced quality, missed deadlines, or additional costs; reviewing and approving contractor progress billings; and evaluating the contractor’s progress. However, we noted problems in each of these areas that impacted the cost and timeliness of the project. Finally, formal guidelines for issuing completion documents are lacking. As a result, construction completion documents for the Lied Library project were subject to varying interpretations and modifications. Because these documents impact life-safety issues and the completion of work, formal guidelines should be established.
Principal Findings
|
· The SPWB did
not use a competitive evaluation process to select the architect to design the
Lied Library. Instead, the SPWB
appointed the architect previously selected to conduct a study of the
University and Community College System’s library needs. A competitive contracting process provides
the framework for selecting an architect on the basis of qualifications and it
documents the contract was awarded fairly. (page 8)
· Although
required by law, the SPWB did not establish a process to evaluate contractors’
qualifications. Consequently, the SPWB
did not evaluate the qualifications of the contractors that bid on the Lied
Library since criteria and procedures had not been established. (page 12)
· Change orders
added $3.6 million to the cost of construction and more than 6 months to the
project completion date. Noteworthy
among the change orders was the construction of certain walls to meet
fire-safety codes. Initial construction
of these walls deviated from the building plans; but, approval from appropriate
regulatory officials was not obtained.
These deviations created several fire-safety issues requiring more than
1 year to resolve. (page 14)
· The SPWB
issued the contractor four construction change directives to proceed with work
related to fire-safety issues. Although
these directives stated labor and materials were not to exceed $115,000, the
SPWB authorized change orders totaling about $690,000 for this work. Despite the impact construction change
directives have on a project’s cost, the SPWB lacks formal policies and
procedures to help ensure they are properly monitored and controlled. (page 15)
· The architect
did not approve seven progress billings totaling $4.7 million because of
concerns regarding the extent of the project’s completion and the sufficiency
of money to complete the project.
Although Board policy and contract terms require the architect’s
approval of all billings, the Board paid these billings without documenting the
resolution of the architect’s concerns. (page 16)
· NRS 341.100
requires the Manager of the SPWB to advise the Board and the Legislature of the
progress of all public works projects.
However, information submitted to these oversight bodies was at times
inconsistent with project records.
Consequently, an accurate status of the construction problems associated
with the Lied Library was not always communicated. (page 17)
· The date a
building is deemed to be substantially complete is a key milestone. For example, the contract provides that
liquidated damages cannot be assessed for work completed after this date. However, there is conflicting information
regarding the date the Lied Library was substantially complete. This raises doubts about compliance with
contract requirements. (page 18)
· The SPWB and
the State Fire Marshal issued a conditional certificate of occupancy for the
Lied Library effective July 6, 2000.
This certificate was issued with four outstanding conditions relative to
fire-safety. As of February 28, 2001,
only one issue had been resolved; therefore, a final certificate had not been
issued as of that date. Despite the
importance of this certificate, guidelines have not been established to
document the conditions that must exist in order to occupy a facility and
resolve outstanding conditions. (page 20)
Agency Response
to Audit Recommendations
Recommendation
Number Accepted Rejected
1 Develop
policies and procedures to ensure the architect selection
process is competitive when projects are funded on the basis of a study. X
2 Legislation be considered addressing contractor qualification criteria. X
3 Adopt
criteria and procedures for evaluating qualifications of
construction firms
bidding on projects as required by law. X
4 Develop
formal guidelines for approval of deviations from construction
plans. X
5 Develop
policies and procedures for approving and monitoring
construction change
directives. X
6 Obtain
the architect’s approval on each progress billing as required
by Board policy. X
7 Develop
policies and procedures to resolve progress billings disputed
by the architect. X
8 Ensure
oversight bodies are provided reliable information regarding
the status of
public works projects. X
9 Develop
formal guidelines for the issuance of a certificate of
substantial
completion and a certificate of occupancy. X
TOTALS 9 0