Audit Division
Audit
Summary
State’s Contracting
Process
LA02-11
The purchasing component of the
Integrated Financial System (IFS) contains a number of controls designed to
ensure that purchasing transactions are properly recorded and executed. However, we identified areas where
internal control weaknesses exist.
For example, vendor payments could be better controlled, discounts are
not always taken, and fixed asset codes need to be consistently entered. These weaknesses were caused, in part,
because the Division’s policies and procedures for the online processing of
purchasing transactions have not been fully developed. In addition, Purchasing staff must enter
incorrect dates to process certain transactions. Further, transactions can be completed
in one fiscal year, but recorded as expenditures in the prior year. As a result, the reliability of
information and the accuracy of budgetary accounting data could be
impacted. The development of sound
internal controls is critical to help ensure the integrity of purchasing
transactions and that management’s directives are carried out.
·
State agencies
did a poor job in planning the contracts we reviewed. Agencies incorrectly identified five of
seven contractors as sole source providers. In addition, agencies did not typically
obtain approval for the use of a sole source provider. Review and approval of the decision not
to seek proposals from other providers is important because these contracts
bypass full and open competition. (page 11)
·
Contracts did
not always contain adequate performance requirements. Contract deliverables were unclear,
expected completion dates were not always specified, and performance incentives
were often lacking. Only 1 of 16
contracts we reviewed contained a penalty provision for poor performance. (page
15)
·
Poor planning
contributes to frequent contract amendments. The BOE approved 27 amendments for the
16 contracts we reviewed. In total,
contract amounts increased more than $5 million from $2.2 to $7.4 million. (page
18)
·
The state’s
contract award process does not ensure vendor proposals are consistently and
objectively evaluated, and contracts are awarded fairly. State agencies used a wide variety of
methods for evaluating vendor proposals.
Only five of nine evaluation methods assigned a score to each proposal as
required by state law. In addition,
none of the proposals were evaluated using a technical evaluation process. (page
19)
·
Evaluation
committees were not always used to evaluate proposals. A committee was not used to evaluate
proposals in three of nine solicitations.
In addition, two committees evaluating proposals did not receive
sufficient guidance to ensure consistent and objective scoring. (page 25)
·
State agencies
did not follow proper contract monitoring practices. Contract Compliance Checklists were not
prepared for 7 of 16 contracts. In
addition, most checklists prepared were incomplete. Further-more, vendor reporting
requirements were not included in 9 of 16 contracts. For the seven contracts with reporting
requirements, only two agencies received reports. (page 26)
·
The Department
of Administration lacks the information it needs to oversee the state’s
contracting activities. Information
regarding state contracts is not complete, accurate, or readily available. In addition, Contract Summary forms
submitted to the BOE are not always accurate. Furthermore, agencies do not always
provide the BOE with adequate justification for their decision to contract.
(page 28)
·
The State does
not ensure employees responsible for contracting activities are adequately
trained. Although the State offers
a contract training course, the training does not provide in-depth coverage on
contract planning, awarding, and monitoring. In addition, attendance is not
required. Other states have
recognized the importance of this training and have developed contract
certification programs to ensure employees have adequate contracting skills.
(page 31)
·
The State does
not have adequate policies and procedures to ensure contracting activities are
properly carried out. In fiscal
year 2000, the BOE and its Clerk approved about 1,900 contracts amounting to
more than $500 million. Without
adequate policies and procedures, the BOE does not have assurance the contracts
it approves are properly planned and awarded, and will be monitored after
approval. (page 33)
· Accountability for the state’s contracting activities is poor. Although the BOE is responsible for approving contracts, it has little involvement in key activities such as planning, awarding, and monitoring. The responsibility for these activities is fragmented throughout state government. Because a framework for accountability has not been established, agencies often delegate contracting functions to employees that may not have adequate skills. In addition, employees may not have proper authority over the function being contracted for, or accept responsibility for ensuring vendor performance. (page 33)
State’s Contracting Process
Agency Response
to Audit Recommendations
Recommendation Number |
|
Accepted |
|
Rejected |
|
|
|
|
|
1 |
Segregate the
responsibilities for entering the information creating
a vendor payment voucher |
X |
|
|
|
|
|
|
|
2 |
Create a report that
will identify discounts available and taken |
X |
|
|
|
|
|
|
|
3 |
Establish a process
to identify those users who consistently fail to include the “FA” code,
providing additional training where necessary |
X |
|
|
|
|
|
|
|
4 |
Develop policies and
procedures for the Division’s use of the extended purchasing component,
including approving payment vouchers, ensuring cash discounts are taken,
and reviewing purchase orders to ensure fixed assets are properly
coded |
X |
|
|
|
|
|
|
|
5 |
Request that
appropriate staff be provided the ability to authorize the continued
processing of a transaction when the error message occurs that indicates
the delivery date is before the transaction date |
X |
|
|
|
|
|
|
|
6 |
Request a system edit
to control the recording of transactions to the wrong fiscal
year |
X |
|
|
|
|
|
|
|
|
TOTALS |
6 |
|
0 |