Audit Division
Audit Summary
Results in Brief
|
Although the Agency for Nuclear Projects’ financial and administrative practices have improved, some weaknesses still exist. Over the last several years the Agency’s federal funding has been declining and its reliance on state funding increasing. Although the state funding had statutory and other requirements, the Agency did not comply with all these requirements. This resulted in about $65,500 of contingency fund money not being reverted at the end of fiscal year 1999. In addition, we issued an audit in 1995 that made several recommendations to improve the Agency’s contracting process. The Agency implemented many of the recommendations, but some of the recommendations could be better addressed. Finally, the Agency does not always follow other contract requirements and its system of management control could be improved.
Principal
Findings
|
·
The
Agency did not request reimbursement from the U.S. Department of Energy for all
possible contract expenditures during fiscal year 1999. Had reimbursement been
requested, the Agency could have returned about $50,000 to the contingency fund
at the end of fiscal year 1999.
·
The
Agency ordered over $23,000 of office supplies, furnishings and equipment
during the last two weeks of June 1999 using emergency contingency funds. About $15,500 of these expenditures do not
appear to fall within statutory requirements for the use of contingency
funds.
·
The
Agency did not always take adequate steps to ensure the contract awarding
process was controlled. The majority of
contracts we reviewed either did not have adequate cost analyses prepared or
did not have evidence that contractors’ qualifications were verified or were
otherwise determined to be acceptable.
·
Many of
the contracts examined did not provide clear descriptions of expected
deliverables. In addition, contract
monitoring could be strengthened to ensure contract payments are appropriate
and contractors comply with all contract terms and other state
requirements.
·
Although
the Agency has developed a procedures manual, the manual could be improved to
ensure better control of the Agency’s financial and administrative
activities. During our review, we
identified several issues where a better control system could have prevented or
detected their occurrence.
to Audit
Recommendations
Recommendation
Number Accepted Rejected
1 Comply
with statutory and other funding requirement. ___X____ _______
2 Seek
reimbursement for all allowable expenditures from the Federal
Government. ___X____ _______
3 Improve
the current procedures for estimating, analyzing, and comparing
contract costs ___X____ _______
4 Develop
procedures for verifying contractor qualifications and reviewing
contractor invoices
to ensure the appropriateness of the payments. ___X____ _______
5 Prepare
contracts that clearly define the contract deliverables. ___X____ _______
6 Require
contractors to submit proof of workers’ compensation insurance
prior to the
commencement of contract work. ___X____ _______
7 Improve
the system of management controls to promote sound financial
and administrative
practices. ___X____ _______
Totals ___7____ ___0___